Starting in May 2025
For any questions or concerns related to the construction of BUSD workforce housing, the contact for the General Contractor’s on-site superintendent is:
Jason Olsen, Superintendent
(888) 302-4304
Click here for information on Longfellow Middle School.
For other questions about the project, please visit our Project and FAQ page, or contact us at .
Below is an anticipated schedule of construction activities taking place for BUSD Workforce Housing. As needed, the schedule will be updated on this webpage.
Demolition / Rough Grading
May – July 2025
Shoring / Earthwork / Underground / Foundations
August – October 2025
Concrete Structure
October – November 2025
Framing/Exteriors
November 2025 – September 2026
Interior Finishes
July 2026 – October 2026
Sitework
October 2026 – January 2027