Construction Updates

Starting in May 2025

Construction Contact Information

Anticipated Schedule of Construction Activities

Below is an anticipated schedule of construction activities taking place for BUSD Workforce Housing. As needed, the schedule will be updated on this webpage.

Demolition / Rough Grading
May – July 2025

Shoring / Earthwork / Underground / Foundations
August – October 2025

Concrete Structure
October – November 2025

Framing/Exteriors
 November 2025 – September 2026

Interior Finishes
July 2026 – October 2026

Sitework
October 2026 – January 2027

Construction Related Documents

BUSD Design Subcommittee Meeting 9/27/2022

Join Us on Tuesday, September 27th, 7 – 8 PM

A public listening session for more information about density, massing, and design feedback of the planned educator workforce housing at 1701 San Pablo.

Zoom Link
Webinar ID: 833 4572 5923
Passcode: 605257

Community Meeting 5/24/2022

A Design Subcommittee Meeting will be held on Tuesday, 5/24 at Berkeley Adult School, 1701 Sab Pablo Avenue, Berkeley, CA 94702 in room 209.

BUSD takes step toward building affordable housing

In a unanimous vote, the board approved the location for a project that could build up to 110 homes for its teachers and staff in the parking lot of the Berkeley Adult School at 1701 San Pablo Ave.

BUSD Workforce Housing Community Conversation

Welcome and Introductions, Satellite Affordable Housing Associates, Abode Communities, Pyatok Architects, Background, Conceptual Design Options, Questions / Comments, Next Steps.